Match List - I with List – II and select the correct answer using
List - I (Term)
A. Dummy activity
B. Critical path
C. PERT activity
D. Critical path methodList -II (Characteristics)
1. Follows β distribution
2. It is built on activity-oriented diagram
3. Constructed only to establish sequence
4. Has zero total slack
b. A→4, B→2, C→3, D→1
c. A→3, B→4, C→2, D→1
d. A→4, B→2, C→1, D→3
asked in Mechanical Paper-2, 2007